Biomass plant in Ely

The locals were blocking the project of construction of power plant, due to potential environmental risks and changing the surroundings

Ongoing conflict? no
Conflict type Bioenergy plants
Resources logging residues
Issues 1 ecological, 2 social, 3 economical, 4 cultural
Keywords conflict, biomass, Ely, pollution, traffic pressure
References http://www.sciencedirect.com/science/article/pii/S0301421502003427#
Start date 1994
End date 1995
Reason(s) for conflict
Intensity public debate
What are the stakeholders' conflicting values or interests investor did not properly consulting development plant with local people, locals were blocking the project of construction of power plant, due to potential environmental risks and changing the surroundings
Barriers for dialogue lack of communication and feasibility actions
Forums for dialogue more transparent position of the investor in public consultations
Suggestions for conflict resolution / transformation joint and trustworthy dialog
Comments

Back